9.0 SELECTION OF BIDDERS
Based on the
comparison analysis, all offers will be collected and a comparative table as
below will be generated. This will save a lot of the time and it also helps the
Technical and Finance Team to make an assessment of the bids received. Table
below shows that the comparison and evaluation table of 7 different bidders
from difference companies. Since prangin mall do not have their own budget
estimation, hence in order to getting the a more reliable budget, the mean of
all quotation submitted is then calculated. After that, the range of the
acceptable price is then calculated which between the 10% value of the mean
calculated. Then, the proposed quotation of companies which did not fall in the
range is automatically been rejected as it is too low or too high cost for the
maintenance work. Then, the company which is not rejected, then, the pranging
will consider the company finance condition, number of project on going and
reputation of the companies. Then only compare which company have lowest cost
for the maintenance work.
No
|
Maintenance
Work
|
Com A
|
Com B
|
Com C
|
Com D
|
Com E
|
Com F
|
Com G
|
(RM)
|
||||||||
1
|
Civil
|
26,515.00
|
24,223.00
|
25,124.50
|
23,780.00
|
32,766.97
|
18,470.50
|
35,453.50
|
2.
|
Mechanical & Electrical
|
22,971.20
|
24,532.60
|
26,113.56
|
20,964.00
|
26,152.80
|
17,332.00
|
26,141.60
|
Total
Quotation (RM)
|
49,486.20
|
48,755.00
|
51,238.06
|
44,744.00
|
58,919.77
|
35,802.50
|
61595.10
|
Table: Proposed Quotation of
Each Company for the Maintenance Work
From the above
quotation the mean and the range calculated is as followed:
Mean = RM 50,077.23
Range: RM45069.51 ~
RM55084.95
From the range, it
shows that, the company D, E, F and G is automatically rejected due to the
quotation proposed is fall out of the range.
Then, the operation
manager chooses the Company B for the maintenance work in prangin mall. This is
because that among them the company B have the lowest quotation and the company
B have clear cash flow and also the good finance condition and not really heavy
project is undergoing in company B. Besides that, Company B They have over 20
years of experiences in managing the maintenance buildings of works. They are
able to provide comprehensive maintenance solutions with high quality standards
of building maintenance management.
The criteria below
have been evaluated in order to select the winner of the bidder which included:
a)
Capability of the participant company to fulfil the
requirement including technical and competence, financial viability and other
relevant experiences
b)
Relevant skills of company provided, experience and
availability of key personnel
c)
Quality assurance requirements
d)
The risks or constraints associated with our offer.
Comments